Sizing and specification

Calculating fleet size

Time per task = travel out empty + pick + travel back loaded + drop + an allowance for queueing and passing

Fleet size = tasks per hour × time per task ÷ 3,600 ÷ availability per machine

Parameter Value
Average travel speed 60–70% of rated speed
Jacking pick and drop 10–15 s each
Underride fork pick and drop 20–30 s each
Forklift, low level 30–45 s each
Forklift, high level 60–120 s each; the upper end for high positions
Tote robot 20–40 s each, by shelf height
Queueing allowance 15–25%; the upper end for narrow aisles and larger fleets
Availability 0.85, after charging, faults and servicing

Average speed is taken at two-thirds of rated because of turning, slowing and passing — the number most often overestimated. Round the result up and add one spare machine. High-level work should be banded rather than averaged: in a high-bay warehouse the top and bottom levels can differ by more than a factor of two, so weight by where the locations actually are.

Need the full engineering documents?

Site survey forms, recommended spare parts lists by model and battery transport documents are provided for each project. Tell us the model and the site, and we will send the latest version.

Request documents

SEE ALSO

All six handling series →  ·  Send your site conditions