Deployment and operation
Who does what
The contract and the scheme should state who performs each item and who pays for it.
Item
Usually
Note
Floor works
User
Scope and standard agreed at scheme stage
Carrier modification
User or agreed
Drawings from Jiangsong; fabrication by the user or a third party
Code laying
Jiangsong or shared
Codes from Jiangsong; the user may help place them
Network
User
Jiangsong gives the specification, the user meets it
Power
User
Supply for chargers and the server
Third-party interfaces
User coordinates
Cooperation from lift, door and line vendors
Mapping and commissioning
Jiangsong
—
Training
Jiangsong
The user names the people to be trained
Unclear responsibility is the main source of dispute — above all on floor works and carrier modification, which cost real money and will be argued about on site if not written down.