Deployment and operation

Six stages

Stage Work Output
1. Survey and scheme Site measurement, requirements, model and fleet size, layout Survey record, configuration, layout drawing, remediation list
2. Site preparation Floor works, carrier modification, code laying, network, power Remediation sign-off
3. Delivery Unpacking, server and system deployment, charger installation Receipt, deployment record
4. Mapping Laser mapping, editing, points and routes, device records Map files, point table, device list
5. Commissioning Single-machine, docking calibration, multi-machine, traffic rules Commissioning record, docking success report
6. Trial and acceptance Continuous running at real takt, exceptions, training, acceptance Trial report, training record, acceptance certificate

Three things sit on the critical path: floor works, which must finish before mapping or the map is redone; third-party interfaces to lifts, doors, conveyors and machines, which take long to coordinate and must start at kick-off; and the network, which has to be measured rather than assumed.