Deployment and operation

Six stages

Stage Work Output
1. Survey and proposal Requirements, site survey, technical proposal and quotation, technical confirmation sheet Written records after each discussion, survey record, technical proposal, technical confirmation sheet, site modifications
2. Site preparation Floor, network and interfaces; rack and carrier modification, QR codes, power Confirmation that modifications are complete
3. Delivery and unpacking Unpacking inspection, server and system set-up, charger installation Unpacking inspection record, deployment record
4. Mapping and routes Laser mapping, map editing, points and routes Map files, point table, equipment list
5. Docking and system commissioning Single-vehicle and docking commissioning, multi-vehicle runs, and linking with upper systems, doors and lifts Commissioning records
6. Trial run, training and acceptance Running at the real cycle time, recording and correcting exceptions, on-site training, acceptance item by item against the technical agreement Training confirmation, acceptance record and test data handed over on the day

Standard products are normally delivered within 45 working days, as stated in the contract. Three things need to start early: floor modifications must be finished before mapping, because a changed floor means a new map; interfaces to third-party lifts, automatic doors, conveyors and machines take time to coordinate and should start at kick-off; and the wireless network must be measured to specification, because problems found only at commissioning are costly to fix.

Need the full engineering documents?

Site survey forms, recommended spare parts lists by model and battery transport documents are provided for each project. Tell us the model and the site, and we will send the latest version.

Request documents

SEE ALSO

Robot projects: survey to acceptance →  ·  Send your site conditions